BTS took part in the construction of an oil collection point in Nizhnekamsk where the major pipeline was commissioned at the AO Transneft facility at the oil metering point. The company also participated in the construction of metal structures at the plant itself being engaged by KamGesFundamentStroy company from Naberezhnye Chelny, republic of Tatarstan.

Строительство очереди заводов НПЗ УЗК Танеко Татнефть (г. Нижнекамск)

Nizhnekamsk is the petrochemical center of the Republic of Tatarstan where starting from 2009 Tatneft has been constructing a huge complex of oil refineries and petrochemical plants which is expected to process 7 mln tons of oil year into a whole bunch of different petrochemical products. BTS took part in the construction of an oil collection point in Nizhnekamsk where the major pipeline was commissioned at the AO Transneft facility at the oil metering point. The company also participated in the construction of metal structures at the plant itself being engaged by Aktuybinskoe SMU company from Aznakayvsky District, republic of Tatarstan. The company also participated in the construction of metal structures at the plant itself being engaged by KamGesFundamentStroy company from Naberezhnye Chelny, republic of Tatarstan.

Client’s requirements: supply of automobile cranes.

Meeting the requirements:  10 automobile cranes with a carrying capacity of 25 tons and 1 automobile crane with a carrying capacity of 50 tons were provided.

The total number of equipment units amounting to 11.

Issued solved in the course of the project:

1. As the construction was being carried out for more than 6 months we had to remove registration from Samara Rostechnadzor office to a Nizhnekamsk one.

2. As the access to the territory of the refinery is limited we were to solve an issue of fuel and spare part delivery.


Project photo report

Ask a Question